Standard Lithium Completes Fabrication of Phases 1 & 2 and Begins Mobilisation of Its “LiSTR” Direct Lithium Extraction Demonstration Plant to the Arkansas Project Site

  • Targeted to Produce 100-150 Tonnes per Annum of Lithium Carbonate
  • First-of-a-kind direct lithium extraction demonstration plant, being deployed in Southern Arkansas

VANCOUVER, British Columbia, Aug. 22, 2019 (GLOBE NEWSWIRE) -- Standard Lithium Ltd. (“Standard Lithium” or the “Company”) (TSXV: SLL) (OTCQX: STLHF) (FRA: S5L), is pleased to announce that the fabrication of Phases 1 & 2 of the Company’s “LiSTR” direct lithium extraction Demonstration Plant are complete, and that the initial modules are currently being transported to the project location at Lanxess’ South Plant facility in southern Arkansas (the “Site”). Standard Lithium is also pleased to confirm that all the Site construction works are on-schedule, and the concrete slab and foundations required to locate the Demonstration Plant have been completed.

Fabrication and initial QA/QC testing of Phases 1 & 2 of the Demonstration Plant have been completed (see press release dated 2nd June 2019) and the modules (9 modules in Phases 1 & 2) have been separated, and prepared for overland shipment. The first modules are currently in transit and expected to arrive at the Site next week. A still-frame from the disassembly video is shown in Figure 1 below.

All of the enabling works required at the project location at Lanxess’ South Plant facility in southern Arkansas are on-schedule (see press release dated 26th June 2019) and the required site drainage, foundations and concrete slab required to locate the first-of-a-kind direct lithium extraction demonstration plant have been completed. A crane has been mobilised to the Site in order to move the modules from the flat-bed trucks to their final installed location, and current image of the Site is provided in Figure 2 below.

The Demonstration Plant is designed to continuously process an input tailbrine flow of 50 gallons per minute (gpm; or 11.4 m3/hr) from the Lanxess South Plant, which is equivalent to an annual production of between 100-150 tonnes per annum Lithium Carbonate Equivalent (LCE). The Demonstration Plant is based on Standard Lithium’s proprietary LiSTR technology, that uses a solid sorbent material to selectively extract lithium from Lanxess’ tailbrine. 

The environmentally friendly process eliminates the use of evaporation ponds, reduces processing time from months to hours and greatly increases the effective recovery of lithium.

Dr Andy Robinson, Standard Lithium President and COO, commented, “The Standard Lithium team and our partners continue to execute on our strategic plan to timely advance our project in Southern Arkansas. Over 2 years of disciplined process design and engineering work has brought us to this point, and we look forward to announcing more real milestone completions in the near-future.

About Standard Lithium Ltd.
Standard Lithium (TSXV: SLL) is a specialty chemical company focused on unlocking the value of existing large-scale US based lithium-brine resources. The Company believes new lithium production can be brought on stream rapidly by minimizing project risks at selection stage (resource, political, geographic, regulatory & permitting), and by leveraging advances in lithium extraction technologies and processes. The Company’s flagship project is located in southern Arkansas, where it is engaged in the testing and proving of the commercial viability of lithium extraction from over 150,000 acres of permitted brine operations. The Company is currently installing a first-of-its-kind Demonstration Plant that will use the Company’s proprietary technology to selectively extract lithium from LANXESS’ tailbrine. This Demonstration Plant will be used to prove commercial feasibility. The environmentally friendly process eliminates the use of evaporation ponds, reduces processing time from months to hours and greatly increases the effective recovery of lithium.

The Company is also pursuing the resource development of over 30,000 acres of separate brine leases located in southwestern Arkansas and approximately 45,000 acres of mineral leases located in the Mojave Desert in San Bernardino County, California.

Standard Lithium is listed on the TSX Venture Exchange under the trading symbol “SLL”; quoted on the OTC - Nasdaq Intl Designation under the symbol “STLHF”; and on the Frankfurt Stock Exchange under the symbol “S5L”. Please visit the Company’s website at www.standardlithium.com.

On behalf of the Board,

Standard Lithium Ltd.
Robert Mintak, CEO & Director

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. This news release may contain certain “Forward-Looking Statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. When used in this news release, the words “anticipate”, “believe”, “estimate”, “expect”, “target, “plan”, “forecast”, “may”, “schedule” and other similar words or expressions identify forward-looking statements or information. These forward-looking statements or information may relate to future prices of commodities, accuracy of mineral or resource exploration activity, reserves or resources, regulatory or government requirements or approvals, the reliability of third party information, continued access to mineral properties or infrastructure, fluctuations in the market for lithium and its derivatives, changes in exploration costs and government regulation in Canada and the United States, and other factors or information. Such statements represent the Company’s current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by the Company, are inherently subject to significant business, economic, competitive, political and social risks, contingencies and uncertainties. Many factors, both known and unknown, could cause results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements. The Company does not intend, and does not assume any obligation, to update these forward-looking statements or information to reflect changes in assumptions or changes in circumstances or any other events affections such statements and information other than as required by applicable laws, rules and regulations.

Photos accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/7ab38850-504c-44c0-b37b-f4d277142aa9

https://www.globenewswire.com/NewsRoom/AttachmentNg/372772a4-82c0-499c-b9b9-f03b6bdc7dee

Contact Information:
LHA Investor Relations, Mary Magnani, (415) 433-3777; standardlithium@lhai.com

Primary Logo

Figure 1

Phase 1 & 2 Modules Being Disassembled and Prepared for Trucking – clip from video taken Aug 06th, 2019
Figure 2

Project Site Location Showing Completed Foundations and Mobile Crane Ready to Install Modules – Image taken Aug 21st, 2019

Source: Standard Lithium